The report states that 181 gigawatts of planned gas-fired power generation capacity in the United States and Europe have been shelved due to delays in connecting to the national power grid.
Research indicates that developers of artificial intelligence data centers are planning to build large-scale, climate-damaging, on-site gas-fired power plants to meet their energy needs.
The findings reveal that, due to obstacles in connecting to national power grids, data center projects in the United States, the United Kingdom, and continental Europe are planning to construct on-site fossil-fuel power plants, totaling 181 gigawatts of gas-fired generation capacity—nearly four times the peak electricity demand of the United Kingdom.
According to research by BloombergNEF, if these plans are carried out, this “rapid power generation” model would result in approximately 345 million metric tons of carbon dioxide equivalent (CO2e) emissions annually in the United States—where 90% of these planned on-site gas-fired plants are located. This is equivalent to the annual greenhouse gas emissions from roughly 72.8 million gasoline-powered vehicles.
This report was released on Wednesday, coinciding with the gathering of global leaders in Turkey for the 31st UN Climate Change Conference (COP31). A central topic of discussion at the summit is the advancement of electrification—ideally powered by clean energy. However, several key European leaders, including those from France and Germany, will not be attending COP31; instead, they are heading to Dublin for the first-ever EU summit on artificial intelligence, taking place this Friday.
Mark Daly, head of data centers and emerging technology at BloombergNEF, stated: “The extraordinary economic benefits offered by artificial intelligence make speed one of the most critical priorities—a defining constraint—for data center developers.”
“Climate outcomes depend not only on how much electricity these facilities consume, but also on how quickly they can be connected to the power grid, and whether the power system can incorporate cleaner forms of generation as demand grows.”
The report states that electricity demand from AI data centers is projected to nearly quadruple by 2035, reaching 2,354 terawatt-hours—equivalent to 7% of global electricity demand.
AI data centers consume vast amounts of power to run servers, cool equipment, and operate facility systems.
Daly notes that while developers of future data centers may claim that their use of gas-fired power generation is merely a temporary measure while awaiting grid connections, the economic incentives once these facilities are online could encourage them to continue using such power—creating a risk of long-term “lock-in” to fossil fuels.
The report points out that ensuring new data centers are connected to the power grid is a more sustainable option. It further emphasizes that accelerating grid connections is crucial for limiting the impact on emissions and mitigating the risk of fossil fuel lock-in.
According to Future Energy Networks, a representative body for the UK’s gas networks, there were over 100 inquiries regarding gas connections for planned data centers in the UK during 2024–2025—a trend driven by delays in securing connections to the electricity grid.
For example, Wapseys Wood in Buckinghamshire and Quest Park in Bedfordshire are seeking to build their own on-site gas-fired power plants due to long wait times for grid connections. These data centers are among the first to be processed through the government’s “fast-track” approval mechanism for Nationally Significant Infrastructure Projects—a system that allows developers to bypass local elected planning authorities to expedite the delivery of large-scale infrastructure.
However, as part of a so-called “data center agreement,” Chancellor John Healey has authorized data centers to construct and operate temporary, on-site fossil-fuel power plants while they await grid connections. This sets a precedent that could lead to more data centers in the UK adopting on-site fossil-fuel power generation.
Oliver Hayes, head of policy and campaigns at Global Action Plan, stated: “For any government serious about climate action, the construction of private gas-fired power plants for data centers should be a red line; it is therefore shocking to see the Chancellor explicitly supporting them.”
“No one can seriously believe that these gas-fired plants are merely temporary—once built, they will continue to generate high emissions for years to come.”